Project Overview
This project was awarded to Schouten Environmental to
completed demolish the existing 140ft fall standing bell tower
and all interior finishes complete with hazardous abatement
Project Scope:
Project consisted of extensive interior building finishes removal
and Type III abatement of ceiling texture within the cathedral
annex vestibule. Exterior works included removal of existing front
façade and salvaging field stone for re-purposing, complete
structure decommissioning of the bell tower and 32 brass bells.
Road closures, rigging and craning of the 2-4ton bells was
completed with no delays or safety concerns for both works and
stakeholders